Practice Quiz: Chapter 09
Quiz Content
*
not completed
.
Which of the following is an example of a project constraint?
a) You must minimize the overall cost of the project
correct
incorrect
b) You must complete the project as quickly as possible
correct
incorrect
c) The overall cost of the project must be less than 5 million dollars
correct
incorrect
d) None of the above
correct
incorrect
*
not completed
.
Which of the following is an example of a project objective?
a) You must minimize the overall cost of the project
correct
incorrect
b) The overall cost of the project must be less than 5 million dollars
correct
incorrect
c) You must complete the project in less than 8 months
correct
incorrect
d) All of the above
correct
incorrect
*
not completed
.
Based on Figure 9.2 on p. 167, which steps do not precede the "Assemble Truss" step?
a) Assemble Penstock
correct
incorrect
b) Transport to Site
correct
incorrect
c) Retender Truss
correct
incorrect
d) Engineering Revision
correct
incorrect
*
not completed
.
What is a possible cause of project delay?
a) Procrastinating
correct
incorrect
b) Overrunning of resources
correct
incorrect
c) Poor planning
correct
incorrect
d) All of the above
correct
incorrect
*
not completed
.
As a project manager, what is not an appropriate response to an overrun deadline due to delay in an activity?
a) Ignore it
correct
incorrect
b) Cancel the project
correct
incorrect
c) Assign additional resources to the delayed activity
correct
incorrect
d) Replace the delayed activity with an alternate activity
correct
incorrect
*
not completed
.
It is possible to spend money to save time in project management.
a) True
correct
incorrect
b) False
correct
incorrect
*
not completed
.
The "critical path" of a project is the path in the activity network graph leading to the shortest time.
a) True
correct
incorrect
b) False
correct
incorrect
*
not completed
.
It is usually cheaper to compensate for an overrun activity early rather than later.
a) True
correct
incorrect
b) False
correct
incorrect
*
not completed
.
Once a project is planned upfront, there is no need for revisiting it during implementation.
a) True
correct
incorrect
b) False
correct
incorrect
*
not completed
.
Gantt charts are a common tool for project management.
a) True
correct
incorrect
b) False
correct
incorrect
Previous Question
Exit Quiz
Next Question
Review all Questions
Submit Quiz